PRJ-042 · Ports, Marinas & Marine Structures
Haifa Submarine Harbour - Deep-Pile Quays and Dry Dock
Deep sheet piles, long tubular piles, two quays and dry dock
In Cooperation with RoyalCompleted; harbour inaugurated 7 December 2015
Ports, Marinas & Marine Structures
Deep-foundation quay and dry-dock phase of the submarine harbour
Installed sheet piles about 26-31 m long; drove approximately 275 42-inch piles to -73 m and approximately 1,000 36-inch piles to -40 m; and constructed two 100 m quays, a dry dock, precast works, concrete and wall beams.
- Location
- Haifa Naval Base, Haifa, Israel
- Client
- Israeli Ministry of Defense / Israeli Navy
- Consultant
- Ministry of Defense Engineering & Construction Department / Navy engineering team (best estimate)
- Value
- Confidential Information